17.24.310    BLASTING PLAN

(1) Each application must contain a blasting plan for the proposed permit area. The plan must explain how the applicant intends to comply with the requirements of ARM 17.24.621 through 17.24.626 and 17.24.1260 through 17.24.1263, and must include the following:

(a) types and approximate amounts of explosives to be used for each type of blasting operation to be conducted;

(b) description of procedures and plans generally used for:

(i) drilling patterns, including size, number, depths, and spacing of holes;

(ii) charge and packing of holes;

(iii) types of fuses and detonation controls;

(iv) sequence and timing of firing holes;

(v) a description of procedures and plans for recording of (i) through (iv) above and retention of those records;

(c) description of blasting warning and site access control equipment and procedures;

(d) description of types, capabilities, sensitivities, and locations of use of any blast monitoring equipment and procedures proposed to be used;

(e) description of plans for recording and reporting to the department the results of preblasting surveys, if required;

(f) description of unavoidable hazardous conditions for which deviations from the blasting schedule will be needed; and

(g) a general description of structures to be protected and a discussion of design factors to be used to protect the public and to meet the applicable airblast, flyrock, and ground vibration standards in ARM 17.24.624.

(2) For underground mines the department may, on a case-by-case basis, waive any of the requirements in (1) of this rule that do not apply to underground blasting operations.

 

History: 82-4-205, MCA; IMP, 82-4-222, MCA; NEW, 1980 MAR p. 725, Eff. 4/1/80; AMD, 1989 MAR p. 30, Eff. 1/13/89; TRANS, from DSL, 1996 MAR p. 3042; AMD, 2024 MAR p. 255, Eff. 2/10/24.


 

 
MAR Notices Effective From Effective To History Notes
17-432B 2/10/2024 Current History: 82-4-205, MCA; IMP, 82-4-222, MCA; NEW, 1980 MAR p. 725, Eff. 4/1/80; AMD, 1989 MAR p. 30, Eff. 1/13/89; TRANS, from DSL, 1996 MAR p. 3042; AMD, 2024 MAR p. 255, Eff. 2/10/24.