HOME    SEARCH    ABOUT US    CONTACT US    HELP   
           
Rule: 38.5.8402 Prev     Up     Next    
Rule Title: APPLICABILITY
Add to My Favorites
Add to Favorites
Department: PUBLIC SERVICE REGULATION
Chapter: UTILITY DIVISION
Subchapter: Small Generator Interconnection
 
Latest version of the adopted rule presented in Administrative Rules of Montana (ARM):

Printer Friendly Version

38.5.8402    APPLICABILITY

(1) The interconnection procedures set forth in this subchapter apply to applicants proposing to install and interconnect a small generator facility to an EDC's system that satisfies the following criteria:

(a) The small generator facility must be sited on the utility customer's premises;

(b) The customer installing the small generator facility must be in good standing with the utility;

(c) The proposed small generator facility's point of interconnection may not be on a transmission line;

(d) The power produced from the small generator facility must be contained on the EDS and not flow onto the transmission system; and

(e) The power exported by an interconnection customer can only be sold to the EDC.

History: 69-3-103, MCA; IMP, 69-3-102, MCA; NEW, 2010 MAR p. 1801, Eff. 8/13/10.


 

 
MAR Notices Effective From Effective To History Notes
38-2-207 8/13/2010 Current History: 69-3-103, MCA; IMP, 69-3-102, MCA; NEW, 2010 MAR p. 1801, Eff. 8/13/10.
Home  |   Search  |   About Us  |   Contact Us  |   Help  |   Disclaimer  |   Privacy & Security