HOME    SEARCH    ABOUT US    CONTACT US    HELP   
           
This is an obsolete version of the rule. Please click on the rule number to view the current version.

17.36.918    HORIZONTAL SETBACKS, FLOODPLAINS

(1) Minimum horizontal setback distances (in feet) are as follows:

 

 

                       TABLE 1

                  SETBACK DISTANCES

 

 

Sealed components (1)
and other

components (2)

Absorption systems (3)

Public or multi-user wells/springs

100

100

Other wells

50

100

Suction lines

50

100

Cisterns

25

50

Roadcuts, escarpments

10 (4)

25

Slopes > 25% (5)

10 (4)

25

Property boundaries

10

10

Subsurface drains

10

10

Water lines

10

10

Drainfields/sand mounds (3)

10

-

Foundation walls

10

10

Surface water, Springs

50

100

Floodplains

--(1)

100 (2)

100

 

(1) Sealed components include sewer lines, sewer mains, septic tanks, grease traps, dosing tanks, pumping chambers, holding tanks and sealed pit privies.  Holding tanks and sealed pit privies must be located at least 10 feet outside the floodplain or any openings must be at least two feet above the floodplain elevation.

(2) Other components include intermittent and recirculating sand filters, package plants, and evapotranspiration systems.

(3) Absorption systems include absorption trenches, absorption beds, sand mounds, and other drainfield type systems that are not lined or sealed.  This term also includes seepage pits and unsealed pit privies.

(4) Sewer lines and sewer mains may be located in roadways and on steep slopes if the lines and mains are safeguarded against damage.

(5) Down-gradient of the sealed component, other component, or drainfield/sand mound.

 

(2) The reviewing authority may require greater horizontal separation distances than those specified in Table 1, if it determines that site conditions or water quality nondegradation requirements indicate a need for the greater distance.

(3) If the floodplain has not been designated and its level relative to a wastewater system is in question, the applicant shall submit evidence adequate to allow the reviewing authority to establish the location of the floodplain.

(4) Sealed components of wastewater treatment systems, if located within a 100-year floodplain, must be designed and constructed to prevent surface water and ground water inundation, and pump lines must be pressure tested prior to use. Pipes must have a pressure rating of at least two times the operating pressure or pump shutoff pressure, whichever is greater.  Pipes must be tested at 1 1/2 times the operating pressure or pump shutoff pressure, whichever is greater, or must be tested as specified by the manufacturer.

History: 75-5-201, MCA; IMP, 75-5-305, MCA; NEW, 2003 MAR p. 222, Eff. 2/14/03.