18.4.201    ALTERNATIVE CONTRACT PROJECT DELIVERY METHODS

(1) Construction manager general contractor experience will not be a required scoring criteria for highway construction projects.

(2)  The department must weight the in-person interview of each shortlisted proposer as at least half of the technical score.  The technical proposal will account for the balance of the technical score.

 

History: 60-2-201, 60-3-101, MCA; IMP, 60-2-111, 60-2-112, 60-2-134, 60-2-201, MCA; Ch. 145, L. 2023, Section 1; NEW, 2023 MAR p. 705, Eff. 7/22/23.


 

 
MAR Notices Effective From Effective To History Notes
18-191 7/22/2023 Current History: 60-2-201, 60-3-101, MCA; IMP, 60-2-111, 60-2-112, 60-2-134, 60-2-201, MCA; Ch. 145, L. 2023, Section 1; NEW, 2023 MAR p. 705, Eff. 7/22/23.